Within an open quote, non-standard labour costs can be added using the left-side panel.
Notes:
- DTU (Decimal Time Unit): 0.1 DTU = 6 minutes (1.0 DTU =1 hour)
- The labour subtotal at the bottom of quotes will not include miscellaneous labour items. Only manufacturer parts and labour from service jobs will be included.
Watch this video to learn more!
To add a non-standard labour cost:
- From the left-side panel, click Labour.

- In the Miscellaneous Labour window, fill in the fields as detailed as possible. Note: This window times out if no action is taken within a few minutes.

Options include:- Labour (DTU)
- Description
- Total Price Excl. VAT
- When ready, click Add.
- The labour cost is added as a line item in the quote.

KB Article #5866